Campos Thermal Power Plant Substation

Projects focused on the implementation and modernization of high voltage substations with an emphasis on efficiency and reliability, conducted with the technical and operational standards that characterize BR Infra.

power transmission brinfra 07

Challenge

Eletrobras required the execution of a critical capacity expansion project at the Campos Thermal Power Plant Substation, in Rio de Janeiro, with an extremely tight deadline: only 80 days between contract signing and the energization of the last transformer.

This short window was established by the local distribution company, representing the only window until 2026 to carry out the intervention without affecting power supply. The challenge was to execute a highly technically complex project within an ambitious schedule, ensuring safety, reliability, and regulatory compliance.

The Solution

BR Infra developed an agile, integrated action plan, prioritizing the following work fronts:

  • Replacement of transformers TR1 and TR3 (138/69/13.8 kV – 73 MVA each);
    Replacement of a 138 kV disconnector;
  • Reconductoring of the 69 kV busbars, carried out using remote live-line work methods.

The construction coordination led by our team was decisive for the project’s success, ensuring engagement from everyone involved, clear communication with stakeholders, and rigorous application of safety standards.

Those who want it, do it. And we do.

The project’s success was ensured by a strategic execution, which involved:

  • Direct integration between BR Infra and Eletrobras for critical decisions;
  • Rigorous schedule management with daily monitoring;
  • Use of specialized live-line work techniques, optimizing execution time;
  • Engagement of the construction team and coordination of third-party teams, ensuring integration among stakeholders.

A safety culture applied across 100% of activities, ensuring employee integrity.

Results Achieved

  • Project completed in a record time of 80 days, meeting the client’s expectations;
  • Increase in transformation capacity from 107 MVA to 166 MVA;
  • Continuity and reliability in the power supply for the region;
  • Assurance that execution would not be delayed until 2026.

Much more than construction

We connect people, energy and progress

More than delivering infrastructure, BR Infra delivers purpose. With a team driven by excellence in execution, we transform challenges into solutions that drive the country’s development.

How can we help?

Fill out the form so our technical team can contact you.

Explore other Projects

Serra – ES

Vitória 345/138/13.8 kV Substation — Stages 20P and 21R

Share on social media

Excellence in Engineering, Procurement and Construction (EPC)

Transform your project with BR Infra's expertise

With 18 years of experience and proven technical capability, BR Infra executes complex projects with integrated management and total focus on performance. Count on those who deliver results that energize Brazil.