Projects focused on the implementation and modernization of high voltage substations with an emphasis on efficiency and reliability, conducted with the technical and operational standards that characterize BR Infra.
Eletrobras required the execution of a critical capacity expansion project at the Campos Thermal Power Plant Substation, in Rio de Janeiro, with an extremely tight deadline: only 80 days between contract signing and the energization of the last transformer.
This short window was established by the local distribution company, representing the only window until 2026 to carry out the intervention without affecting power supply. The challenge was to execute a highly technically complex project within an ambitious schedule, ensuring safety, reliability, and regulatory compliance.
BR Infra developed an agile, integrated action plan, prioritizing the following work fronts:
The construction coordination led by our team was decisive for the project’s success, ensuring engagement from everyone involved, clear communication with stakeholders, and rigorous application of safety standards.
The project’s success was ensured by a strategic execution, which involved:
A safety culture applied across 100% of activities, ensuring employee integrity.